Support the Arctic Sea Ice Forum and Blog

Author Topic: Arctic ice breakers and US Coast Guard updates  (Read 2530 times)

morganism

  • Young ice
  • Posts: 2936
    • View Profile
  • Liked: 309
  • Likes Given: 193
Arctic ice breakers and US Coast Guard updates
« on: July 21, 2024, 12:32:19 AM »
Coast Guard Polar Security Cutter (Polar Icebreaker) Program: Background and Issues for
Congress

Summary
Required number of polar icebreakers. A 2023 Coast Guard fleet mix analysis concluded that
the service will require a total of eight to nine polar icebreakers, including four to five heavy
polar icebreakers and four to five medium polar icebreakers, to perform its polar (i.e., Arctic and
Antarctic) missions in coming years.

Current operational polar icebreaker fleet.

The operational U.S. polar icebreaking fleet currently consists of one heavy polar icebreaker, Polar Star, and one medium polar icebreaker, Healy. A second Coast Guard heavy polar icebreaker, Polar Sea. Polar Sea, suffered an engine casualty in June 2010 and has been nonoperational since then. Polar Star and Polar Sea entered service in 1976 and 1977, respectively, and are now well beyond their originally intended 30-year service lives. The Coast Guard plans to extend Polar Star’s service life until the delivery of at least the second Polar Security Cutter (PSC; see next paragraph).

Polar Security Cutter (PSC).
The Coast Guard Polar Security Cutter (PSC) program aims to acquire four or five new PSCs (i.e., heavy polar icebreakers), to be followed at some later point by the acquisition of new Arctic Security Cutters (ASCs) (i.e., medium polar icebreakers).
The Coast Guard in 2021 estimated PSC procurement costs in then-year dollars as $1,297 million (i.e., about $1.3 billion) for the first ship, $921 million for the second ship, and $1,017 million (i.e., about $1.0 billion) for the third ship, for a combined estimated cost of $3,235 million (i.e., about $3.2 billion). The PSC program has received a total of about $1,731.8 million in procurement funding through FY2024. The Coast Guard’s proposed FY2025 budget requests no procurement funding for the PSC program. One oversight issue concerns the accuracy of the PSC’s estimatedprocurement cost, given the PSC’s size and internal complexity as well as cost growth in other Navy and Coast Guard shipbuilding programs. If substantial cost growth occurs in the PSC
program, it could raise a question regarding whether to grant some form of contract relief to the
PSC shipbuilder. Another oversight issue concerns the delivery date for the first PSC: the Coast
Guard originally aimed to have the first PSC delivered in 2024, but the ship’s estimated delivery
date has been delayed repeatedly and may now occur no earlier than 2029.

Commercially available polar icebreaker (CAPI).
The Coast Guard’s proposed FY2024 budget requested, and the FY2024 Department of Homeland Security (DHS) Appropriations Act (Division C of H.R. 2882/P.L. 118-47 of March 23, 2024) provided, $125.0 million in procurement funding for the purchase of an existing commercially available polar icebreaker (CAPI) that would be modified to become a Coast Guard medium polar icebreaker. The ship the Coast Guard intends to purchase and modify is Aiviq, a U.S.-registered ship that was originally built to serve as an Arctic oil-exploration support ship, and which has an icebreaking capability sufficient for the ship to serve following modification as a Coast Guard medium polar icebreaker. The Coast Guard’s proposed FY2025 budget requests no procurement funding for the CAPI program.
The Coast Guard’s FY2025 Unfunded Priorities List (UPL) includes an item for $25.0
million in procurement funding for the ship.

Great Lakes icebreaker (GLIB). The Coast Guard’s FY2024 budget initiated a program for
procuring a new Great Lakes icebreaker (GLIB) that would have capabilities similar to those of
Mackinaw, the Coast Guard’s existing heavy GLIB. The FY2024 DHS Appropriations Act
(Division C of H.R. 2882/P.L. 118-47 of March 23, 2024) provided $20.0 million in procurement
funding for the GLIB program. The Coast Guard’s proposed FY2025 budget requests no
procurement funding for the program. The Coast Guard’s FY2025 UPL includes an item for $25.0
million in procurement funding for the program.
(more)

https://crsreports.congress.gov/product/pdf/RL/RL34391



.....

Coast Guard Cutter Procurement:  Background and Issues for Congress

https://crsreports.congress.gov/product/pdf/R/R42567
Kalingrad, the new permanent home of the Olympic Village

morganism

  • Young ice
  • Posts: 2936
    • View Profile
  • Liked: 309
  • Likes Given: 193
Re: Arctic ice breakers and US Coast Guard updates
« Reply #1 on: July 23, 2024, 09:07:10 PM »
(x-post from the politics thread. No specifics in the report, tho does mention faster than expected warming effects on permafrost and coastal erosion)

(...)

It builds upon guidance laid out in the 2022 National Security Strategy and 2022 National Defense Strategy and is part of DODs effort to implement the 2022 National Strategy for the Arctic Region.

"This strategy is very action oriented, which distinguishes it from previous Arctic Strategies" Deputy Assistant Secretary for Arctic & Global Resilience Iris Ferguson said. "We unpack where we need to sustain our investments, especially in critical capabilities. What do we have to see? How do we communicate? Do we have the right equipment to operate in the region? My office exists to champion these capabilities, which are vital to the successful implementation of our strategy."

The Arctic region is undergoing rapid change, both strategically and physically. The People's Republic of China (PRC), which remains DOD's pacing challenge, seeks increasing access and influence in the Arctic, while Russia remains an acute threat in the region despite its losses in Ukraine. Increasingly, these two competitors are collaborating in the Arctic with implications for the security of the United States and our Allies and partners. At the same time, Finland and Sweden's historic decision to join NATO brings all like-minded Arctic states into the NATO Alliance and presents new opportunities for collaboration and cooperation. All of this is underscored by the impact of climate change on the Arctic, which is warming at least three times faster than the rest of the world and increasingly opening to more human activity.

To address this dynamic security environment, DOD will adopt a "monitor-and-respond" approach to the Arctic, supported by robust domain awareness cooperation with our highly capable Allies and partners, and underpinned by the deterrent value of DOD's ability to deploy the Joint Force globally at the time and place of our choosing. The ways DOD will execute this approach are grouped into three main lines of effort:

    DOD will enhance its capabilities to campaign in the Arctic especially its domain awareness, communications, and intelligence, surveillance, and reconnaissance capabilities.
   
DOD will engage with Allies and partners to uphold defense and deterrence in the Arctic, build interoperability, and increase its understanding of how to operate in the region.

    DOD will exercise calibrated presence in the Arctic by regularly training in the region and conducting routine operations critical to upholding deterrence and homeland defense.

You can read the full strategy on the DoD website here.

https://media.defense.gov/2024/Jul/22/2003507411/-1/-1/0/DOD-ARCTIC-STRATEGY-2024.PDF
Kalingrad, the new permanent home of the Olympic Village

morganism

  • Young ice
  • Posts: 2936
    • View Profile
  • Liked: 309
  • Likes Given: 193
Re: Arctic ice breakers and US Coast Guard updates
« Reply #2 on: July 24, 2024, 11:09:12 PM »
Op-Ed: Senator Kelly Throws U.S. Maritime Industry a Lifeline — Let’s Seize It

https://gcaptain.com/op-ed-senator-kelly-throws-u-s-maritime-industry-a-lifeline-lets-seize-it/

....

Senators Kelly and Rubio, Representatives Waltz and Garamendi Release National Maritime Strategy Report

https://www.kelly.senate.gov/newsroom/press-releases/senators-kelly-and-rubio-representatives-waltz-and-garamendi-release-national-maritime-strategy-report/

Today, Senator and 25-year Navy combat veteran Mark Kelly (D-AZ) and Representative and combat-decorated Green Beret Mike Waltz (R-FL-6), along with Senator Marco Rubio (R-FL) and Representative John Garamendi (D-CA-8), released the bipartisan report entitled “Congressional Guidance for a National Maritime Strategy” that provides a comprehensive vision for planning guidance, strategic objectives, and actionable steps to revitalize the nation’s maritime sector. 

The legislators believe that, in an era of great power competition, aging infrastructure, and the threat of high intensity war, Congress must adopt a maritime strategy vital to U.S. national security and the world. Unfortunately, despite calls from Congress for the last decade, such a comprehensive strategy has yet to be produced.   

“After decades of neglect, revitalizing the American maritime industry will supercharge our economy and strengthen our national security,” said Sen. Kelly, a U.S. Merchant Marine Academy graduate and Navy veteran. “Our bipartisan report provides a roadmap for the administration and Congress to work together to rebuild our shipbuilding sector and fortify the U.S.-flag fleet. It won’t be easy, but America has always been a maritime nation—and the stakes are too high for us to fail.”

....

CONGRESSIONAL GUIDANCE FOR A NATIONAL MARITIME STRATEGY

https://www.kelly.senate.gov/wp-content/uploads/2024/05/Congressional-Guidance-for-a-National-Maritime-Strategy.pdf
Kalingrad, the new permanent home of the Olympic Village

morganism

  • Young ice
  • Posts: 2936
    • View Profile
  • Liked: 309
  • Likes Given: 193
Re: Arctic ice breakers and US Coast Guard updates
« Reply #3 on: August 01, 2024, 12:08:49 AM »
Finnish firm eyes opportunity from Biden’s decision to replace Chinese port cranes

In February this year, president Joe Biden signed an executive order setting in place a plan to replace the nation’s Chinese-built port cranes over concerns they could be fitted with spy devices. Biden has earmarked $20bn over the next five years to get Chinese cranes replaced.

The world’s largest port crane manufacturer, Shanghai Zhenhua Heavy Industries (ZPMC), has repeatedly denied claims from US politicians that its equipment poses a cybersecurity threat. Nevertheless, the Biden administration is determined to push forward with its crane replacement programme.

Konecranes has announced it is establishing a network of partners to build a full range of port cranes in the US, joining Japan’s Mitsui in building cranes on American soil.

The network developed by Konecranes is comprised of US steel structure providers and subcontractors to satisfy domestic manufacturing criteria including ‘Build America Buy America’.

Konecranes is now able to manufacture a full range of domestic manufacturing-compliant port cranes in the US including ship-to-shore cranes

Analysts at Alphaliner, a container shipping consultancy, believe that the US government’s initial aim to replace all Chinese-made cranes in the country’s ports by newbuilt cranes within a fairly short period appears unrealistic.

“Potentially, the new legislation could be watered down after the presidential elections, so that Chinese-made equipment must be replaced at the end of its economic lifetime, which could be around 2040 for some of the recently-installed cranes,” Alphaliner suggested in its latest weekly report.

https://splash247.com/finnish-firm-eyes-opportunity-from-bidens-decision-to-replace-chinese-port-cranes/
Kalingrad, the new permanent home of the Olympic Village

morganism

  • Young ice
  • Posts: 2936
    • View Profile
  • Liked: 309
  • Likes Given: 193
Re: Arctic ice breakers and US Coast Guard updates
« Reply #4 on: August 01, 2024, 09:24:04 PM »
Arctic glaciers serve as namesake for 2 future coast guard vessels
Surveillance ships part of Canada's plan to strengthen its Arctic presence

A ceremonial good-luck coin has been welded into the keel of one of the Canadian Coast Guard's two future Arctic and offshore patrol ships — both of which will be named after glaciers.

The names of the CCGS Donjek Glacier and the CCGS Sermilik Glacier were announced Wednesday at Halifax's Irving Shipbuilding, where the keel of the Donjek Glacier is already complete.

The Donjek Glacier is named after a glacier in Yukon's Kluane National Park. The Sermilik Glacier's namesake is found in Nunavut's Sirmilik National Park — and its name is an Inuktitut word meaning "place of glaciers."

Once fully built, the primary purpose of these two ships will be to support fisheries enforcement and surveillance missions along Canada's East Coast.

As a secondary function, the ice-ready ships will be able to both assist in search-and-rescue missions and icebreaking operations and also strengthen Canada's position in the Arctic, Dartmouth-Cole Harbour MP Darren Fisher said at the unveiling.

"We want to ensure that the Canadian Coast Guard has everything they need to protect Canada's marine environment while ensuring our country's sovereignty by maintaining a strong presence in our water, especially in the Arctic," Fisher said.

The two vessels are being built as part of the country's national shipbuilding strategy. The contract was first announced in May 2019 and construction of the Donjek Glacier began in August 2023.

The ships will replace two of five similar patrol vessels in the Canadian Coast Guard's fleet.

As of the end of 2023, more than $26.5 billion in total contracts had been awarded under the strategy.
Broader emphasis on Arctic security

Canada has been putting greater emphasis on Arctic security.

Earlier this month at the NATO summit in Washington, Canada announced a pact with the United States and Finland to build icebreakers for the region.

Russia has 40 icebreakers, with more in production, and China considers itself a "near Arctic power."

Also at the NATO summit, Defence Minister Bill Blair said that Canada is taking the first steps to procure up to 12 conventionally powered, under-ice submarines to replace the aging Victoria-class fleet.

Following the release of the defence policy update in the spring, both Blair and Prime Minister Justin Trudeau indicated it's a matter of when Canada begins buying new submarines — not if.

The Canadian government also confirmed its purchase of a strategically located 21,000-square-foot aircraft hangar in Inuvik, N.W.T., earlier this month for $8.6 million.

The move received praise from northerners and security experts after foreign buyers showed interest in the hangar.

As reported by CBC in June, Canada is in talks with Germany and Norway for a trilateral security pact focused on the North Atlantic and Arctic waters. As part of these talks, Canada has been invited to join a submarine procurement program involving the two other friendly nations.

The German-Norwegian partnership is expected to begin delivering boats in 2026, but that date remains in flux.

https://www.cbc.ca/news/politics/coast-guard-ship-naming-halifax-arctic-1.7281053?cmp=rss

Kalingrad, the new permanent home of the Olympic Village

kassy

  • First-year ice
  • Posts: 9183
    • View Profile
  • Liked: 2233
  • Likes Given: 2048
Re: Arctic ice breakers and US Coast Guard updates
« Reply #5 on: August 02, 2024, 05:30:14 PM »
Naming ice breakers after glaciers is just bad taste.
Þetta minnismerki er til vitnis um að við vitum hvað er að gerast og hvað þarf að gera. Aðeins þú veist hvort við gerðum eitthvað.

morganism

  • Young ice
  • Posts: 2936
    • View Profile
  • Liked: 309
  • Likes Given: 193
Re: Arctic ice breakers and US Coast Guard updates
« Reply #6 on: August 24, 2024, 12:28:57 AM »
Congressional Report Details New Delays and Cost Overruns for Coast Guard

The bad news for the U.S. Coast Guard’s Polar Security Cutter program keeps on coming. A new Congressional Budget Office (CBO) report details further cost overruns and delays for the program originally authorized in 2019.

Most significantly, little progress has been made on finalizing the vessel’s design over the past several years. According to the CBO as of July 2024 the vessel’s design remains at only 59 percent complete, even less than the 67 percent the Government Accountability Office reported in May of this year.

Progress on the vessel’s functional and traditional design has seen progress at a glacial pace over the past three years, with maturity continuing to hover around the 50 percent mark.

Despite this lack of progress Coast Guard leadership continues to express confidence that construction on the first PSC, tentatively named Polar Sentinel, will begin before the end of the year. The GAO warned that beginning construction before reaching 100% design maturity increases program risks and may lead to delays down the line.

The new CBO report estimates cost overruns for the procurement of three PSC at $5.1 billion, 60 percent above the Coast Guard latest estimates. The increase comes in part due to the late-stage design changes increasing the vessel’s size by 40 percent from 13,000 tons to 18,000 tons; a cost addition the Coast Guard has not fully taken into account the report explains.

Lifetime costs for operation and mission support will total $12.4 billion between 2029 and 2063.  If the USCG were to acquire additional vessels – the service says it may need up to five heavy icebreakers – costs would nearly double to $21.2 billion. The Coast Guard’s budget for FY 2025 stands at $13.8 billion.

In order to have a continuous 2.5 icebreaker-presence the Coast Guard estimates it will require an eight or nine-ship fleet when factoring in maintenance.

Both existing icebreakers, Healy and Polar Star, are out of service this summer following an onboard fire and scheduled dry dock time, leaving the U.S. without surface vessel presence in the Arctic.

The timeline for service entry of Polar Sentinel has now slipped into 2029 the CBO report details, a full 10 years after the contract was awarded.

In contrast, it took only 5 years from authorization to commissioning of the Coast Guard’s last heavy icebreaker from 1971 to 1976.

The delays are a symptom of naval construction in the U.S. generally, the report states.

“The shipyards that built the Polar Star and the Healy have closed, and no existing shipyard in the United States has built a heavy polar icebreaker since before 1970.”

Yards face difficulties hiring new qualified workers and retaining the existing workforce.

“A generation of longtime senior shipyard workers have retired or will soon be retiring. As a result, the workforces in many of those yards are, overall, less experienced than they were in the past,” the CBO concludes.

https://gcaptain.com/congressional-report-details-new-delays-and-cost-overruns-for-coast-guard-icebreaker/

...

https://invidious.poast.org/watch?v=iCsit-HWu48
Kalingrad, the new permanent home of the Olympic Village

morganism

  • Young ice
  • Posts: 2936
    • View Profile
  • Liked: 309
  • Likes Given: 193
Re: Arctic ice breakers and US Coast Guard updates
« Reply #7 on: August 30, 2024, 08:08:02 PM »
U.S. Coast Guard Has A Working Heavy Icebreaker Again

USCGC Polar Star returns to service amid a glaring U.S. icebreaker capacity gap that was made worse by a recent fire.

The U.S. Coast Guard’s heavy icebreaker USCGC Polar Star has returned to its home port of Seattle, Washington, after a major service life-extending overhaul – and not a moment too soon. The medium icebreaker USCGC Healy, the service’s only other icebreaker available for operations in the Arctic and Antarctica, also sailed back into Seattle earlier this month after suffering a fire that forced its crew to abandon a planned deployment to the High North. You can read more about that incident, which shined a glaring light on the inadequacy of the Coast Guard’s icebreaker fleets, in the War Zone‘s previous reporting here.

Polar Star sailed back into Seattle on August 25 following the completion of the fourth phase of a Service Life Extension Project (SLEP) at Mare Island Dry Dock (MIDD) in Vallejo, California. The ship was away from home for 285 days, of which around 140 days were actually spent on the overhaul. The SLEP has been ongoing in this incremental way since 2021 and is set to keep the ship, which first entered service in 1976, operational at least through next year.

As part of phase four of the SLEP “boiler support systems were recapitalized, including the electrical control station that operates them,” and “the heating, ventilation and air conditioning (HVAC) system was refurbished through the overhaul of ventilation trunks, fans and heaters that supply the cutter’s berthing areas,” according to a release the Coast Guard put out yesterday. “The flooding alarm system was redesigned, providing the ability to monitor machinery spaces for flooding from bow to stern.”

“Additional work not typically completed every dry dock included removing and installing the starboard propulsion shaft, servicing and inspecting both anchor windlasses, inspecting and repairing anchor chains and ground tackle, cleaning and inspecting all main propulsion motors and generators, installation of an isolation valve to prevent seawater intrusion into the sanitary system, and overhauling the fuel oil purifier,” the release adds.
(more)
https://www.twz.com/news-features/u-s-coast-guard-has-a-working-heavy-icebreaker-again
Kalingrad, the new permanent home of the Olympic Village

morganism

  • Young ice
  • Posts: 2936
    • View Profile
  • Liked: 309
  • Likes Given: 193
Re: Arctic ice breakers and US Coast Guard updates
« Reply #8 on: September 21, 2024, 02:29:49 AM »
Aker Arctic @AkerArctic
Sep 18
Polarstern, named after the star directly above the North Pole, has arrived under its namesake star.

This is the 8th time the German polar research vessel has reached the top of the world.

spri.cam.ac.uk/resources/inf…

(I didn't know @scottpolar maintained such a list!)
Dr Céline Heuzé
@ClnHz
Sep 18
Hi from the #NorthPole. It is... white
#Arctic #PS144

https://nitter.poast.org/AkerArctic/status/1836493531604750614#m
Kalingrad, the new permanent home of the Olympic Village

morganism

  • Young ice
  • Posts: 2936
    • View Profile
  • Liked: 309
  • Likes Given: 193
Re: Arctic ice breakers and US Coast Guard updates
« Reply #9 on: September 22, 2024, 09:22:18 PM »
Yörük Işık  @YorukIsik   Sep 18

Operation of the Northern Sea Route is impossible without nuclear icebreakers: Russian Government owned ROSATOM State Nuclear Energy Corporation’s Murmansk based subsidiary Federal State Unitary Enterprise ATOMFLOT’s new floating dock is getting towed thru Bosphorus to BlackSea.

https://nitter.poast.org/YorukIsik/status/1836394502916821171#m

Kalingrad, the new permanent home of the Olympic Village

morganism

  • Young ice
  • Posts: 2936
    • View Profile
  • Liked: 309
  • Likes Given: 193
Re: Arctic ice breakers and US Coast Guard updates
« Reply #10 on: November 16, 2024, 07:10:20 PM »
U.S., Finland and Canada agree to icebreaker collaboration pact


Political leaders in the United States, Finland and Canada announced Wednesday that the three nations will build world-class icebreakers for the Arctic and polar waters.

President Joe Biden, Canadian Prime Minister Justin Trudeau and Finland President Alexander Stubb agreed to the Icebreaker Collaboration Effort Pact in a memorandum of understanding.

"We have embarked on a transformative partnership that strengthens our ability to uphold international rules and maintain security in the Arctic and Antarctic regions," the three leaders said in a news release issued by the U.S. Department of Homeland Security.

Biden, Trudeau and Stubb initially agreed to the ICE Pact during a NATO Summit in Washington in July and formalized the agreement with the memo of understanding.

"By jointly developing and producing world-class Arctic and polar icebreakers, we are laying the foundation for a resilient and competitive shipbuilding industry capable of meeting both national and global demand for these critical assets," the leaders said.

They said the agreement "underscores our collective commitment to peace, stability and prosperity in the Arctic and polar regions."

Building icebreakers faster and on a larger scale while combining resources helps to lower costs to build the specialty vessels.

The pact says the three nations will work together to share information, knowledge and resources to design and build world-class icebreakers to keep shipping lanes open in the Earth's polar regions.

The agreement also provides for enhanced exchange of information, workforce development and greater engagement among allies and their partners, according to the Department of Homeland Security.

The pact further supports greater research and development of world-class icebreakers while supporting high-quality manufacturing jobs in the maritime infrastructure industry, according to the DHS.

https://www.energy-daily.com/reports/US_Finland_and_Canada_agree_to_icebreaker_collaboration_pact_999.html

....
In this new #ICEPact article, my colleague Rickard Lindholm and I explore Finland's icebreaker fleet, highly developed maritime cluster, and more!


https://www.wilsoncenter.org/article/icebreaking-explained-finland-europes-icebreaker-superpower

...
Kalingrad, the new permanent home of the Olympic Village

morganism

  • Young ice
  • Posts: 2936
    • View Profile
  • Liked: 309
  • Likes Given: 193
Re: Arctic ice breakers and US Coast Guard updates
« Reply #11 on: December 16, 2024, 01:01:25 AM »

With venerable ship’s retirement, U.S.-led ocean-drilling program ends
JOIDES Resolution stripped of equipment after budget gap left unfilled
U.S. drilling ship JOIDES Resolution

After 192 expeditions, the 46-year-old JOIDES Resolution now sit in a Norwegian harbor, its laboratories stripped and its staff gone.

By retrieving rocks from under the sea, the 46-year-old JOIDES Resolution (JR), the flagship of the U.S.-led International Ocean Discovery Program (IODP), traveled through time. Across 192 expeditions, it drilled samples tracing swings over the past few million years in ocean currents responsible for the Asian monsoon, extracted 25-million-year-old sediments to track the ebb and flow of the early Antarctic ice sheet, and probed the 66-million-year-old geological boundary left by the dinosaur-killing asteroid impact. But in September, the U.S. National Science Foundation (NSF) retired the vessel when no new partner country materialized to fill a budgetary gap. The JR, owned by the shipping firm Sea1 Offshore, now sits in the harbor of Kristiansand, Norway, its laboratories stripped of equipment, its staff laid off or reassigned.

“It was the best of the best of international collaboration,” says Kristen St. John, a marine sedimentologist at James Madison University who co-led the JR’s last cruise in August. Leadership in scientific ocean drilling now shifts to China, which this year unveiled a brand-new, dedicated drill ship, the Meng Xiang. “For the U.S. to not have a next step in place is very disappointing,” St. John says.

U.S. scientists had been scrambling to find a partner country willing to contribute $20 million to the program, adding to the $48 million mandated by Congress. Such a bump would have kept IODP and the JR going for the next half-decade. But the search came up empty. Although the U.S. House of Representatives has drafted a spending bill for this fiscal year that would increase funding to $60 million, that level, even if approved, would likely fall just short of keeping the JR going. Time is now running out, says Anthony Koppers, a marine geologist at Oregon State University and leader of the effort to keep the JR alive. “After 6 months, it becomes less viable to restart a ship like that.”

The remains of IODP will now become IODP3, a smaller program melding Europe and Japan’s previous contributions to IODP. The Japanese have long operated an advanced scientific drilling ship, the Chikyu, but it does commercial oil and gas work and is deployed sparingly for science, just once or twice a year and mostly in Japanese waters. Under IODP3, “We have plans to extend field operations for Chikyu to the west Pacific and Indian ocean,” says Gilbert Camoin, an IODP3 leader and director of the agency that manages European drilling.

Europe, meanwhile, has no dedicated drilling platform, but instead hires commercial ships for specific missions. Beginning in spring 2025, the first IODP3 expedition will follow this plan, hiring a commercial ship to drill into the continental shelf south of Martha’s Vineyard, an island off the coast of Massachusetts, to explore the mystery of why freshwater from inland aquifers seems to invade the ocean, rather than vice versa. NSF will help fund the work even though it is not officially part of IODP3, Camoin says.

The United States will also hire commercial drill ships for occasional research cruises until it builds or redevelops a dedicated drilling ship. Plans for that ship are underway, says Carl Brenner at Columbia University, who directs IODP’s U.S. science support program. But it will likely take more than a decade to get it done. “Our community is resourceful and I’m sure some great science will get done,” he says. “But there’s no escaping that there will be less of it.”

https://www.science.org/content/article/venerable-ship-s-retirement-u-s-led-ocean-drilling-program-ends
Kalingrad, the new permanent home of the Olympic Village

morganism

  • Young ice
  • Posts: 2936
    • View Profile
  • Liked: 309
  • Likes Given: 193
Re: Arctic ice breakers and US Coast Guard updates
« Reply #12 on: December 25, 2024, 08:59:35 PM »
New Coast Guard Heavy Icebreaker Construction Finally Underway

The first Polar Security Cutter was supposed to have been delivered this year but construction has just began after multiple delays.

The construction of the first Polar Security Cutter (PSC) heavy icebreaker for the U.S. Coast Guard is now formally proceeding. Though the milestone is important, it also underscores the PSC program’s already massive delays. The first of these new icebreakers was originally supposed to have been delivered this year and now may not arrive until 2029. The Coast Guard is sorely in need of more heavy icebreakers, with only one such ship, which is aging and increasingly hard to maintain, in its current fleet.

The Integrated Program Office for the PSC, which the Coast Guard runs together with the U.S. Navy, received approval to proceed with building the first PSC on Dec. 19, according to a press release yesterday. Bollinger Mississippi Shipbuilding in Pascagoula, Mississippi, is the current prime contractor for the new icebreakers. VT Halter Marine was originally hired to design and build three of the ships in 2019. Bollinger acquired VT Halter Marine in 2022.
(snip)
As already noted, the Coast Guard currently has one heavy icebreaker in service, the USCGC Polar Star, which displaces some 13,840 tons with a full load. The PSCs are expected to be substantially larger, displacing around 17,690 tons. Heavy icebreakers, in general, are “defined as ships that have icebreaking capability of 6 feet of ice continuously at 3 knots, and can back and ram through at least 20 feet of ice,” according to a report from the National Research Council of the National Academies.

Having just two ocean-going icebreakers presents obvious operational limits and increases the risks of capacity gaps, as was underscored just earlier this year. Healy suffered a fire that cut its planned deployment short in July. At that time, Polar Star was undergoing phase four of its SLEP. This meant the Coast Guard had no medium or heavy icebreaking capacity at all until Polar Star returned to its home port in August. Healy has also since returned to service and wrapped up a 73-day Arctic deployment on Dec. 12.

The question now is when the new PSCs will actually enter service. The mention of the “innovative approach to shorten the delivery timeline” in the Coast Guard’s press release yesterday reflects the substantial delays the program has suffered to date. As mentioned, the lead ship was originally supposed to have been delivered this year. The second and third PSCs would then follow in 2026 and 2027. The schedule slips have been blamed in the past primarily on problems in finalizing the core design. As it stands now, the initial example may not arrive until 2029, a decade after the initial contract award. Concerns are growing about potential cost overruns, as well. There are additional plans to eventually acquire new Arctic Security Cutter (ASC) medium icebreakers, but that effort has yet to begin in earnest.

The Coast Guard has acquired an additional existing ocean-going icebreaker, the Aiviq, off the commercial market. However, it’s unclear when that ship will enter operational service as it still requires unspecified “minimal modifications” to meet the requirements for its new U.S. government role. The vessel will be homeported in Juneau, Alaska, and renamed Storis, in honor of a previous Coast Guard light icebreaker of the same name with an impressive service career spanning from 1942 until 2007. At the time of its decommissioning, the previous USCGC Storis was the oldest operational ship in Coast Guard inventory.
(more)

https://www.twz.com/sea/new-coast-guard-heavy-icebreaker-construction-finally-underway
Kalingrad, the new permanent home of the Olympic Village